When opening a new quarry, producing aggregate for an infrastructure project or recycling demolition waste, the first strategic decision is: a mobile (tracked) plant, a modular (skid/chassis-mounted) plant, or a stationary plant? This decision affects everything from the investment amount to the cost per tonne, from permitting to staffing needs.
The right answer depends on the project. In this guide we compare the three plant types and discuss the questions to ask and the cost items to take into account when deciding.
Three Plant Types
Mobile (tracked) plants
The crusher, feeder, screen and conveyors sit on their own tracked chassis and usually run on diesel-hydraulic or diesel-electric drive. They can move themselves around the site and start production within a few hours. A typical configuration: mobile jaw crusher + mobile cone or impact crusher + mobile screen.
Modular (skid-mounted, portable) plants
Machines are mounted on steel chassis or modules that can be transported by road. They are set up on light foundations or concrete blocks and run on grid electricity. Installation takes from a few days to a few weeks; if needed, they can be moved to another site.
Stationary plants
Permanent plants built with reinforced concrete foundations, steel structures, large bins and long conveyors. They have the highest capacity and the lowest operating cost per tonne; on the other hand, investment and installation time are the longest.
Comparison Table
| Criterion | Mobile | Modular | Stationary |
|---|---|---|---|
| Initial investment (for the same capacity) | High (per machine) | Medium | High (including civil works) |
| Installation time | Hours–days | Days–weeks | Months |
| Operating cost per tonne | Highest (fuel, track maintenance) | Medium | Lowest |
| Capacity | Low–medium | Medium–high | High–very high |
| Movement within the site | Excellent | Limited | None |
| Process flexibility (extra screens, washing, sand) | Limited | Good | Best |
| Maintenance access | Compact, difficult | Good | Best |
| Energy source | Diesel / hybrid / grid | Grid (or generator) | Grid |
| Resale value | High | Medium–high | Low |
8 Questions to Ask When Deciding
- How long will the project or quarry last? For a road project of a few months, mobile; for a quarry with decades of reserves, stationary is the natural choice.
- What is the annual production target? At high tonnages, the stationary plant’s per-tonne advantage quickly covers the difference in investment.
- How close to the quarry face should the crushing point be? Taking a mobile crusher to the face reduces truck haulage; this is a big saving at sites with high truck costs.
- Is grid electricity available? If not, the cost of running on diesel or generators must be taken into account.
- How many different products will be produced? If many fractions, washing and sand production are needed, a stationary or modular plant provides flexibility.
- How abrasive and hard is the material? Very hard, abrasive rock needs large cone crushers and large screen areas, which favours a stationary plant.
- What are the environmental and permit conditions? For temporary projects, permitting for a mobile plant is usually simpler; stationary plants near residential areas need comprehensive dust and noise measures.
- What about the maintenance team and access to spare parts? Mobile equipment brings additional maintenance items such as the diesel engine, hydraulics and track system.
Cost Items: Visible and Invisible
- Investment: Machine price, civil works (foundations, retaining walls), electrical infrastructure, installation.
- Energy: In mobile diesel plants, fuel is the largest operating item. In systems running on grid electricity, energy costs fall markedly. See our energy efficiency guide.
- Wear parts: Independent of plant type, but dependent on crusher size and setting.
- Truck haulage: In the quarry, the face-to-crusher distance increases over time with stationary plants; the cost per tonne-km is often overlooked.
- Staff: Stationary plants can run with fewer operators through more automation; mobile plants are flexible but need operator attention per machine.
- Availability: In stationary plants, surge bins and redundant conveyors buffer stoppages; in a mobile train, when one machine stops the whole line stops.
Hybrid Solutions
Many successful operations combine both approaches:
- A mobile primary crusher at the quarry face + a stationary secondary-tertiary plant fed by conveyor; reduces truck haulage.
- A mobile screen next to the stationary plant for special products or temporary increases in demand.
- Starting with a mobile plant and moving to a modular or stationary plant as the market and reserves become clear.
Recycling Projects
In recycling concrete, asphalt and demolition waste, mobile plants reduce haulage by crushing where the waste arises and can be moved easily between projects. For details in this area, see our article on recycling construction and demolition waste.
Frequently Asked Questions
Is the capacity of a mobile crusher lower than a stationary crusher?
For the same type of crusher, capacities may be similar; but in mobile plants the crusher size is limited by transport limits and the screening area is smaller. Total plant capacity is therefore usually lower than for stationary plants.
How many times can a modular plant be moved?
A properly designed modular plant can be moved many times during its life. Transport costs and the time for foundations and electrical connections should be taken into account.
Can a mobile plant run on grid electricity?
Diesel-electric and fully electric mobile equipment can be connected to the grid; this significantly reduces fuel costs and emissions.
A Simple Cost Comparison Framework
To evaluate the choice between mobile and stationary plants with numbers, you can compare total cost per tonne using the following items:
- Capital cost (per tonne): (Investment − expected scrap/resale value) ÷ total tonnes to be produced over the project.
- Energy/fuel (per tonne): Diesel consumption × fuel price, or kWh × electricity price.
- Wear parts (per tonne): Depends on crusher type and material; may be similar for both options.
- Maintenance (per tonne): Diesel engine, hydraulics and track maintenance are additional items on mobile plants.
- Staff (per tonne): Operators and maintenance team.
- Truck haulage (per tonne): Face-to-crusher distance × cost per tonne-km.
- Installation and relocation: Foundations for modular/stationary plants; transport and site preparation for mobile plants.
In short projects, the share of capital cost per tonne is high, so mobile plants come out ahead; in long projects, the differences in energy and maintenance accumulate and make the stationary plant more advantageous. At sites with high truck haulage costs, using a mobile primary crusher near the face can change this balance.
The Rise of Modular Plants
In recent years, modular plants that combine the capacity and flexibility of stationary plants with the quick installation of mobile plants have become widespread. In a modular design:
- Crusher, screen and feeder modules are pre-wired and tested at the factory,
- On site, light foundations or steel legs are used instead of heavy reinforced concrete,
- Modules can be rearranged in different combinations,
- When the project ends, the plant can be dismantled and moved to another site.
For medium-term quarry projects and operations with growth potential, modular plants are a good balance point.
Maintenance Differences on Mobile Equipment
- Diesel engine maintenance (oil, filters, cooling system) is added to crusher maintenance.
- Hydraulic systems (track drive, adjustment and folding cylinders) need frequent checks for cleanliness and sealing.
- The track system wears when moved frequently around the site; tensioners and rollers should be checked.
- Because of the compact design, liner and screen changes are done in a tighter space; the manufacturer’s maintenance tools are important.
- Dust can cause cooling problems in compact engine compartments; radiators should be cleaned frequently.
An Example from the Field: A Hybrid Approach
At a limestone quarry, the face was moving further from the stationary plant every year and truck costs were rising. The plant installed a mobile primary crusher near the face and a conveyor line connecting it to the stationary plant. The number of trucks fell, fuel consumption decreased and the stationary plant’s secondary-tertiary circuit began to be fed more steadily. This solution could not have been achieved with either a fully mobile or a fully stationary approach.
More Questions
Which crusher types are available as mobile plants?
Mobile versions of jaw, cone, impact and VSI crushers are common; a complete train can be built with mobile screens and stockpile conveyors.
Is product quality from mobile plants as good as from stationary plants?
Good product quality can be achieved with the right crusher and screen combination; but because screening area and additional processes such as washing are limited, stationary or modular plants are more flexible for multi-fraction products with strict specifications.
Do permit processes vary by plant type?
Yes. For temporary projects, the processes for mobile plants may differ; for permanent plants, environmental and building permits are more comprehensive. Current regulations and local practice should be assessed at the start of the project.
What Is a Mobile Crusher and How Does It Work?
A mobile crusher is a crushing unit in which the crusher, feed hopper, feeder, often a pre-screen and product conveyors are combined on a single tracked or wheeled chassis, running on its own diesel engine or a mains connection. Once moved to site it is set up and producing quickly, and it can be tracked to a new position as the quarry face advances.
- Material is tipped into the feed hopper by an excavator or loader.
- A vibrating feeder feeds the crusher steadily; its grizzly section removes fines, which bypass the crusher.
- The crusher (jaw, cone or impact) reduces the material.
- The product conveyor transfers crushed material to a stockpile or to the next mobile unit (e.g. a mobile screen); an overband magnet, if fitted, removes steel.
| Mobile Unit | Duty | Guide |
|---|---|---|
| Mobile jaw crusher | Primary crushing, recycling | Jaw crusher |
| Mobile cone crusher | Secondary and tertiary crushing, hard rock | Cone crusher |
| Mobile impact crusher | Limestone, asphalt and concrete recycling | Impact crusher |
| Mobile screen | Separating products into fractions | Vibrating screen |
For daily maintenance and spare parts of mobile crushers see our mobile crusher maintenance guide, for an introduction to crusher types our what is a crusher guide, and for cost items our crusher prices guide.
How many tonnes does a mobile crusher crush?
Depending on crusher type, size, setting and material, from a few tens to several hundred tonnes per hour. Capacity is directly linked to feeding and pre-screening.
What jobs is a mobile crusher suitable for?
Temporary infrastructure projects, recycling, work across several sites, operations where the face advances continuously, and trial production before investing in a fixed plant.